Supply Quality inspector for NEM JURONG COGEN project locate in Singapore, Shop fabrication and assembly module at Sattahip yard, Thailand.

Witnessed WPS/ PQR and Welder qualification for LAWI Engeineering Co.,Ltd. Power plant boiler erection and installation of industrial waste power plant 9.9 MWe.


Supply qualified welding inspector and QC Engineer and also consulting support Kong Pattana Engineering Co., Ltd. (KEC) to achieve the owner/ client representative audit


Man power Supply QC Engineer for long term period to support water tube boiler site installation and MDR documentation for AMK service and supply Co., Ltd. (MEI of supply bagasse firing traveling KSL project)


Resident inspector for Freeport LNG project Vacuum Insulate Piping (VIP) 276 spools fabrication at CryEng (Thailand) shop fabrication.


Witnessed visual & dimensional inspection, full water test and documentation along with King Mongkut’s University of Technology North Bangkok for HDPE tank at S.R PE GROUP COMPANY LIMITED.

EM BV, Siemens Beni Suef Burullus New Capital project, Resident inspector long term services for HRSG boiler casing fabrication of 8 units in Thailand vendor, Vatana Phaisal Engineering Co., Ltd. (VPE)